The ChargeX EV-EVSE Interoperability Test Plan
What the EEITP of the ChargeX Consortium is (version 2.0, July 2025, maintained by Argonne), how its test cases are organised and described, the Navigator app that browses them, and how it relates to the worked test cases of this tool.
What it is
The EV-EVSE Interoperability Test Plan (EEITP) was written by the testing task force of the ChargeX Consortium, with researchers from Argonne, Idaho and the National Renewable Energy Laboratory. It aims at a common way to test whether a car and a charger work together, drawing on ISO, SAE, OCPP and related standards. Version 1.0 came first; version 2.0 was released in July 2025, and Argonne maintains it as a living document.
Version 1 drew on three internal test plans from industry, review by seven experts, four inputs from a ChargeX survey and a workshop. The procedures were tried out and refined at CharIN North America Testivals in the ChargeX prescribed testing program (Interoperability test events, CharIN Testivals and the first public test data).
How it is organised
Version 2.0 holds 118 detailed test cases, some with several variants, in 17 test types under three categories. The workbook states that the test cases cover 17 of the 26 ChargeX Minimum Required Error Codes (MRECs).
| Category | Test types (number of test cases) |
|---|---|
| Baseline functionality and safety | Authentication types, methods and timeouts (16); idle error faults, EVSE only (5); power transfer (19); session initialization, from authentication to power transfer (8) |
| Advanced charging | Adapters (3); charge discovery protocol (4); dynamic bidirectional power transfer (3); OCPP smart charge profile (7); pause and resume (4); pilot wake (3); scheduled bidirectional power transfer (1); seamless retry (10); simultaneous charging from one dispenser (4); smart charge scheduling (10) |
| Single PKI | Basic certificate validity (6); revocation of EVSE and contract certificates (9); revocation of Sub-CA 2 certificates (6) |
The fields of a test case
| Field | What it holds |
|---|---|
| Nr | The test case number |
| Test Category and Test Type | Where the case sits in the tree above |
| Test Name and Purpose | What is tested and why |
| Test Conditions | What must be set up before the steps: vehicle state, authentication type, protocol, certificates and so on; variants are numbered here |
| Steps | The actions, in order |
| Pass Criteria | What must happen for a pass, per variant |
| Observed Metrics | What to record while running the case |
| Intended MRECs and Other Possible MRECs | The error codes the charger should report when the case provokes a fault, and others it may report |
| Applicable OSI Layer | The layer the case exercises |
| Repeatability requirement | Whether the result must be repeated to count (yes for 75 cases, no for 43) |
| Estimated Duration | Planning time for the case |
| Electrical Safety Level | The safety precaution the case needs: an electrically safe work condition for most (108), lock-out, tag-out and zero voltage verification for 10 |
| Test Case Notes | Remarks |
The same structure appears in a PDF with one table per test case and in a Word template for recording results.
The Navigator app
- The ChargeX-ITP Navigator is a standalone Windows program: a tree of categories, types and test cases on the left, the test table of the chosen case on the right, ready to print.
- It is built from the Excel workbook: a Python script turns each row into an HTML test table, a small Flask server and a JavaScript tree serve them, and PyInstaller packs everything into one executable. The builder scripts are in the repository, so an updated workbook can be turned into a new Navigator.
- Windows may block the downloaded executable; the README explains how to unblock it.
The repository also holds the three reports of the ChargeX prescribed testing program at CharIN Testivals (June 2024, November 2024 and May 2025).
How it relates to the test cases in this tool
- The EEITP is an interoperability plan: a real car with a real charger, judged by what the driver would experience and by the error codes the charger reports.
- The worked test cases in AC test cases, worked, DC test cases, worked and Backend, Plug and Charge and payment test cases are written for this tool in its own structure (Anatomy of a test case): each names the evidence a capture should show and the checks that look at it.
- They overlap in topic (pause and resume, authorization, certificate revocation, smart charging) but not in text or numbering. Running an EEITP case with a tracer on the cable gives the capture that explains a fail (Recording a charging session for analysis).
The EEITP repository has no licence file; its README calls the plan an open source deliverable of ChargeX. This page therefore describes and links the plan and does not reproduce its test cases. Ask Argonne before copying them.
Sources
- Argonne National Laboratory: ChargeX EV-EVSE Interoperability Test Plan (EEITP), version 2.0, July 2025; README, the test plan workbook and the ChargeX-ITP Navigator; no licence file
- ChargeX Consortium: EEITP, pointer repository to the Argonne original
- EV-EVSE Interoperability Test Plan (EEITP) V2.0, workbook, sheets Detailed Test Cases and Information & Comments: fields, categories, counts, version history
- ChargeX-ITP Navigator Builder, README, how the Navigator is built from the workbook
- INL: Minimum Required Error Codes by ChargeX
- INL: ChargeX