Heavy duty trucks and the Megawatt Charging System

Battery electric trucks charge in depots with CCS and on long haul routes with MCS: what changes with megawatt power, how MCS differs from CCS in connector, signalling and data link, the AFIR targets for heavy vehicles, and what this tool can read from an MCS capture.

The setting

Regional and urban trucks charge overnight in the depot, mostly with the same CCS chargers as buses and vans (Depot charging for bus, van and truck fleets). Long haul trucks must add hundreds of kilowatt hours during a driver break, which CCS with its cable and contact limits cannot deliver; that gap is what the Megawatt Charging System closes. Involved are truck makers, charger makers, the operators of truck charging corridors, logistics companies and the road and energy authorities that fund the corridors.

MCS compared with CCS

CCS (DC)MCS
ConnectorIEC 62196-3 (CCS1, CCS2)A new coupler (IEC TS 63379), with a standardised inlet position on the vehicle
Current and powerHundreds of amperesUp to 3000 A at 1250 V quoted as design targets, about 3.75 MW
Analogue signallingControl Pilot states and PWM (IEC 61851-1)Separate signal contacts, no Control Pilot PWM
Data linkHomePlug Green PHY powerline on the Control Pilot, with SLAC (ISO 15118-3)Single pair Ethernet 10BASE-T1S (ISO 15118-10), no SLAC
MessagesDIN SPEC 70121, ISO 15118-2 or ISO 15118-20ISO 15118-20 only
Station standardIEC 61851-23IEC 61851-23 family: IEC 61851-23-3:2026 for MCS

The MCS: the Megawatt Charging System page explains each row. For a capture the important consequence is the last layer: everything above the data link is ISO 15118-20 as in a car, so the app handshake, service discovery, authorization and DC charge loop look the same.

The documents behind MCS are published. SAE issued J3271 on 5 March 2025 as a Technical Information Report. IEC published IEC TS 63379:2026, the coupler for megawatt DC charging up to 1500 V DC and 3000 A, on 28 January 2026, and IEC 61851-23-3:2026, the DC supply equipment of megawatt charging systems with up to 1250 V DC on the vehicle side, on 20 August 2026.

The current classes these documents standardise and the MCS specific service identifiers of ISO 15118-20 could not be confirmed for this page. Check the SAE and IEC texts before citing them.

Rules and corridors

  • AFIR sets targets for heavy duty vehicles too: by 31 December 2027, along half of the TEN-T core network, recharging pools of at least 2,800 kW with at least two points of 350 kW or more each (as summarised by the ICCT, Europe: AFIR, Type 2, CCS2 and ISO 15118).
  • The NEVI minimum standards in the US describe sites with CCS ports for cars; programs for truck charging in North America are not covered here (Charging around the world).
  • Germany: the HoLa project commissioned the first public MCS charging point in Germany in September 2025, at the Lipperland Süd service area on the A2 motorway: a 1.2 MW charger made by ABB E-mobility and operated by EnBW. The project plans eight MCS points at five sites.

Other public MCS sites and their dates, and truck charging programs outside Europe, are not described here because they could not be confirmed from their own sources for this page.

What fails and what to test

  • Everything that fails in a CCS DC session can fail here: app handshake, authorization, cable check, pre-charge and the charge loop (Highway and urban fast charging hubs).
  • New with MCS: the Ethernet link has to come up before any message, the signal contacts replace the Control Pilot states, and the liquid cooled cable adds its own temperature derating.
  • Record the Ethernet frames of the 10BASE-T1S link with a tap that can see both directions, together with the signal contact states and the DC voltage and current. Test the start with the truck parked at the edges of the approach zone, a stop from each side, and a derating by cable temperature. DC test cases, worked has the DC forms.

In this tool

  • A capture whose ISO 15118-20 messages arrive with no HomePlug frame shows SLAC as not in the capture rather than not reached, and the facts name the link: PLC, Ethernet without SLAC, or CAN (SPEC FR-STD-02). A bench tap behind the modem looks the same, and the facts say so.
  • Above the link the analysis is that of any ISO 15118-20 session: HS-01 and HS-02 for the app handshake, IS20-08 for the selected service and parameter set, and the other IS20, SQ and TIM checks. The iso20 demo shows such a session.
  • The MCS specific parts, its service identifiers and pilot signalling, are not decoded.