Europe: AFIR, Type 2, CCS2 and ISO 15118

How public charging is regulated in the European Union: the connectors the law names, the targets and payment rules of the Alternative Fuels Infrastructure Regulation (EU) 2023/1804, the ISO 15118 dates of its delegated act, the data duties, and how far the network has come.

The region at a glance

The European Union sets the rules for public charging in one regulation, AFIR (Regulation (EU) 2023/1804), which applies in every member state since 13 April 2024 and replaced Directive 2014/94/EU. Delegated acts under AFIR fix the technical standards, among them ISO 15118. Member states add their own rules on top, for example calibration law for billing by energy.

AspectEuropean Union
AC connectorType 2 (EN IEC 62196-2)
DC connectorCombo 2, also called CCS2 (EN IEC 62196-3)
Car to charger communicationISO 15118-2 for newly installed public points from 8 January 2026; ISO 15118-20 for new or renovated points from 1 January 2027 (Delegated Regulation (EU) 2025/656). Older DC equipment also speaks DIN SPEC 70121, see DIN SPEC 70121: DC charging, the early CCS protocol
BackendAFIR asks for digitally connected points and open data but, in the sources read for this page, names no backend protocol. The Open Charge Alliance maps the AFIR duties onto OCPP, see OCPP: the charger's link to its backend
Key regulationsDirective 2014/94/EU (common connectors, points from 18 November 2017); AFIR (EU) 2023/1804 (applies from 13 April 2024); Delegated Regulation (EU) 2025/656 (ISO 15118 from 2026 and 2027)
Testing and certificationISO 15118 conformance (Conformance testing: ISO 15118-4, -5 and Testivals); in Germany a type examination under calibration law for billing by energy (Billing and measurement testing); electrical safety and radio, see Safety and type approval of chargers and cars

Connectors and the law that names them

  • Directive 2014/94/EU made Type 2 the common AC connector and Combo 2 the common DC connector for public points. Points deployed or renewed from 18 November 2017 had to meet its Annex II.
  • AFIR repealed the directive and carries the technical specifications on in its own Annex II, so Type 2 and Combo 2 stay the reference connectors.
  • Delegated Regulation (EU) 2025/656 updates the references to the 2022 editions, EN IEC 62196-2:2022 and EN IEC 62196-3:2022, for newly installed or renovated points, and replaces the old wording on interchangeability with compatibility requirements.

A point may carry other connectors as well; the law sets what must at least be there. Connectors compared compares the families, and IEC 62196: plugs, sockets, connectors and inlets explains the standard behind Type 2 and Combo 2.

The exact scope of Annex II (which connectors are required on which points, the rules for L category vehicles and buses) is taken from summaries of AFIR and 2025/656 and is to be checked against the published texts.

AFIR targets on the road

AFIR sets two kinds of targets. The fleet based target ties public power to the cars registered in each member state: at least 1.3 kW of publicly accessible charging power per battery electric car or van, and 0.8 kW per plug-in hybrid (Article 3). The distance based targets fix recharging pools along the trans-European transport network (TEN-T), in each direction of travel (Articles 3 and 4).

Vehicles and networkBy end of 2025By end of 2027By end of 2030
Cars and vans, TEN-T core, a pool at least every 60 kmPool of 400 kW or more, with at least one point of 150 kW or morePool of 600 kW or more, with at least two points of 150 kW or moreAs 2027
Cars and vans, TEN-T comprehensiveNo targetOn half the network: pool of 300 kW or more with one point of 150 kW or moreThe same on the whole network
Trucks and buses, TEN-TOn 15 percent of the network: pools of 1400 kW or more with one point of 350 kW or moreOn half the network: 1400 kW (2800 kW on the core) with one point (two on the core) of 350 kW or moreEvery 60 km on the core with 3600 kW or more, every 100 km on the comprehensive network with 1500 kW or more

Where the network stands: the European Alternative Fuels Observatory (EAFO) counted 1,157,551 public recharging points in the EU27 in its August 2026 data update, 15.2 percent more than in July 2025. Transport & Environment reported in July 2026, from data of June 2026, that 79 percent of the core network already met the 2025 target for 150 kW chargers, that 20 of 27 member states had met their 2027 target on the comprehensive network, and that every member state but one met the fleet based target; trade press named Malta as the one.

AFIR also sets targets for urban nodes and safe and secure truck parking areas, which this page does not list. The heavy duty figures are taken from the official summary of AFIR and a trade analysis; check them against Article 4 before relying on them.

Paying and prices

  • Ad hoc charging: at publicly accessible points deployed from 13 April 2024, a driver must be able to charge without a contract, paying with a payment instrument widely used in the Union (Article 5).
  • At 50 kW or more the operator accepts electronic payment through a payment card reader or a contactless device that can at least read payment cards.
  • Below 50 kW a device that uses an internet connection for a secure payment, such as a specific QR code, is enough.
  • From 1 January 2027 all publicly accessible points of 50 kW or more along the TEN-T road network or in a safe and secure parking area must offer one of those payment devices, including points installed before 13 April 2024, which are retrofitted where needed.
  • At 50 kW or more the ad hoc price is a price per kWh, with an optional occupancy fee per minute, and both are shown before the session starts.
  • Below 50 kW all price components are made available before the session, in a fixed order that starts with the price per kWh and the price per session.

For a capture, ad hoc payment means the authorization often happens outside ISO 15118: the card terminal and the backend decide, and the car sees External Identification Means (EIM). Payment, roaming and Plug and Charge follows a payment through car, charger and backend; the ocpp-rejected demo shows what a refused authorization looks like on the wire.

The precise wording of the price rules comes from summaries by the Commission, the German Nationale Leitstelle Ladeinfrastruktur and operators; check it against Article 5.

Connected, smart and open data

  • Digitally connected: by 14 October 2024 all publicly accessible points had to be digitally connected recharging points, according to the questions and answers of the Commission on AFIR.
  • Smart recharging: publicly accessible points built after 13 April 2024 or renovated after 14 October 2024 must be able to carry out smart recharging, where the current delivered to the battery is adjusted in real time.
  • Data (Article 20): since April 2025 operators provide static data (location, number and type of connectors, opening hours) and dynamic data (availability, operating status) free of charge through the national access points. German bodies published a DATEX II data profile for it, and operator guides expect all Article 20 data in DATEX II from April 2026.
  • Bidirectional: in their national reports member states assess, every three years, what bidirectional recharging could contribute to lower costs and a higher share of renewable electricity (Article 15).

Which points the smart recharging duty covers (for example only normal power points) and the DATEX II date are taken from operator and vendor summaries and are to be checked against Articles 5 and 20 of AFIR.

ISO 15118 in the delegated act

Delegated Regulation (EU) 2025/656 of 2 April 2025 supplements AFIR with the standards for recharging points and makes EN ISO 15118 binding. The summaries read for this page agree on two steps:

FromWhich pointsWhat they support
8 January 2026Newly installed or renovated publicly accessible pointsEN ISO 15118 parts 1 to 5, including ISO 15118-2:2016
1 January 2027Newly installed or renovated points, public and privateEN ISO 15118-20:2022

Suppliers such as Bender describe the 2026 duty as a new obligation for AC charging stations. With ISO 15118 on the line come TLS, certificates and, for -20, bidirectional services: ISO 15118-2: the first generation application layer, ISO 15118-20: the second generation and Plug and Charge and its PKI explain them.

The Charging Interface Initiative (CharIN) published a position paper on 28 April 2026 that says the wording leaves open how compliance is to be shown and how manufacturers of chargers and cars should implement it, and proposes a phased, harmonised introduction of ISO 15118-20.

Whether the 2027 step covers DC points, which parts and editions apply, and whether Plug and Charge must be offered or only supported, are the questions CharIN raises. Read Article 2 and the Annex of 2025/656 for the equipment you test.

Buildings, radio, metering and national rules

In Germany billing by energy falls under calibration law (Eichrecht): the charge point is a measuring system, its readings are signed, and the customer can check them with transparency software. Energy metering and signed meter values describes the scheme and Billing and measurement testing how a charger is examined for it.

Not yet checked against primary sources for this page, and so not described here: the charging point duties for buildings in the recast Energy Performance of Buildings Directive (EU) 2024/1275; the Radio Equipment Directive 2014/53/EU and its cybersecurity requirements for chargers with radio modules; and the national rules of Germany (Ladesäulenverordnung, the Deutschlandnetz program), France, the Netherlands and Norway.

In this tool

  • The analyzer reads the ISO 15118-2, ISO 15118-20 and DIN SPEC 70121 sessions that AFIR points speak. HS-01 to HS-03 check which protocols the car offers and the charger picks, so a capture shows at once whether a charger answers with ISO 15118-20.
  • The TL checks look at the TLS handshake that ISO 15118 brings with it, including the TLS 1.3 profile of ISO 15118-20 (TL-05, TL-06). The pnc-expired demo shows a session that fails on an expired charger certificate.
  • The IS20 checks follow an ISO 15118-20 session: the selected service, the control mode and the discharge limits of bidirectional transfer. The iso20 demo is a clean DC session.
  • The OCPP tool reads the backend log next to the capture, which is where ad hoc payment and remote authorization show up.
  • An EVSEID starting with a European country code keeps the default limit profile (IEC 61851-1 and ISO 15118-2); see Limit profiles: the numbers behind every check.

The analyzer checks what happens on the wire. It does not test whether a charger meets AFIR, Eichrecht or any other law.

Sources