Australia and New Zealand

Type 2 for AC and CCS2 for DC, with CHAdeMO still found on Japanese imports. The wiring rules, the national and state programs that pay for public charging, the rules those programs attach, and the charger counts with their dates.

At a glance

ItemAustraliaNew Zealand
AC connectorType 2 (IEC 62196: plugs, sockets, connectors and inlets), on cars built for the market since 2019 as the NRMA and RAA describe itType 2; Type 1 inlets on older Japanese imports such as the Nissan Leaf
DC connectorCCS2, the default plug for government supported sites; some older sites also carry CHAdeMO: DC charging over CANCCS2 and CHAdeMO: DC charging over CAN: the national guidance asks DC sites for one tethered cable of each
High level communicationPLC: DIN SPEC 70121: DC charging, the early CCS protocol, ISO 15118-2: the first generation application layer, ISO 15118-20: the second generationPLC for CCS2; CAN for CHAdeMO
BackendOCPP: the charger's link to its backend 2.0.1 encouraged for funded sites; South Australia requires OCPP 1.6 or an equivalentNot set by a national rule found in this review
Mains230 V, 50 Hz (verify)230 V, 50 Hz (verify)
Public charging programNational Electric Vehicle Strategy (April 2023); Driving the Nation Fund; state grant programsGoal of 10,000 public charge points by 2030; zero interest loans since 2025

The mains values are the nominal supply of both countries as general references give them. AS 60038 sets the standard voltages for Australian 50 Hz systems; its text was not read for this page.

Standards and installation rules

  • Wiring: AS/NZS 3000 (the Wiring Rules) governs the installation in both countries. The Electric Vehicle Council notes that the 2018 edition added provisions for EV charging installations. A New Zealand Energy Safety review (released under the Official Information Act) proposed changes to AS/NZS 3000:2018 so that neutral and earth may be switched for EV charging circuits.
  • Equipment safety: the Electrical Equipment Safety System (EESS) of the Australian and New Zealand regulators published Information Bulletin 20-013 (October 2020) on the minimum requirements for EVSE. It names the Australian adoption of IEC 61851 among the applicable standards, together with AS/NZS 3820, the essential safety requirements. Equipment in the medium and high risk levels must be registered in the EESS database and carry the RCM mark.
  • Guidance: Standards Australia published SA TS 5396:2024 (EV chargers for residential use) and SA TS 5397:2024 (EV chargers for commercial applications) on 27 September 2024, funded through the NSW Environmental Trust.
  • New Zealand: WorkSafe (Energy Safety) publishes the Electric Vehicle Charging Safety Guidelines in two parts. They supplement or modify AS/NZS 3000 for EV charging, ask for a dedicated final subcircuit, recommend load management for home charge points above 20 A and a yearly test of the charge point and its protective devices. An addendum to the third edition appeared in January 2026.

The exact designations and editions of the Australian and New Zealand adoptions of IEC 61851 (for example an AS IEC 61851.1) and the wiring rule clauses on EV charging were not confirmed from the standards catalogue in this review.

Rules attached to public money

The Australian Government Department of Climate Change, Energy, the Environment and Water (DCCEEW) published minimum operating standards for government supported public charging. They apply to projects that start on or after 1 January 2024, and the states and territories agreed small updates in August 2025. The main points:

South Australia goes further for every new hard wired charger, funded or not. Regulation 58A of the Electricity (General) Regulations 2012 adds demand response. Since 1 July 2024 a charger in scope may only be installed if it is registered with the Technical Regulator and supports OCPP 1.6 edition 2 (or later), ANSI/CTA-2045-B, or a method the regulator deems to comply. It must be able to stop or prevent charging on a remote instruction (DRM 0 or DRM 1) and to limit the charging rate (DRM 2).

For a test lab this means a charger sold into South Australia needs a working OCPP link even for home use, and the smart charging messages of OCPP are part of what the regulator expects. See Smart charging: schedules, limits and grid signals and Backend, Plug and Charge and payment test cases.

National and state programs in Australia

The federal government released the National Electric Vehicle Strategy on 19 April 2023, with three objectives: more affordable EVs on offer, the systems and infrastructure for a fast uptake, and more demand. Charging money flows mainly through the Driving the Nation Fund, run with the Australian Renewable Energy Agency (ARENA).

ProgramWhoWhat the sources report
National highway networkFederal government and NRMA, Driving the Nation FundA$39.3 million towards 117 fast charging sites, about one every 150 km on national highways (ministerial release, 2023)
Ultra fast highway networkARENA and Evie NetworksA$15 million for the first phase of a A$50.2 million network: 42 sites with at least two 350 kW chargers each
Ultra rapid networkARENA and ChargefoxA$6 million towards at least 21 sites from Brisbane to Adelaide and around Perth, about 200 km apart
NSW EV fast charging grantsNSW GovernmentRound 3 (July 2024): A$54 million for up to 140 stations, within a A$149 million program of about 280 fast and ultra fast stations
NSW kerbside charging grantsNSW GovernmentRound 1 approved 671 ports at 391 sites in Sydney and Newcastle; round 2 offered A$4.5 million
Destination Charging Across VictoriaVictorian Government, ZEV RoadmapA$5 million for 141 fast charging stations at 116 sites, 11 kW to 100 kW, so that every town is within an hour of a fast charger
Queensland Electric Super HighwayQueensland Department of Transport and Main Roads, built by Yurika54 fast charging locations when complete; DC with CHAdeMO and CCS2, AC through a Type 2 socket (bring your own cable)
WA EV NetworkWestern Australian Government, delivered by Synergy and Horizon PowerA$43.5 million; 110 fast charging points at 49 locations over about 7,000 km, from Mundrabilla to Kununurra

How many chargers

The Electric Vehicle Council's State of EVs 2025 report counted 1,272 fast charging locations and 4,192 high power public plugs in Australia, up 20 and 22 percent. New South Wales had 357 locations (214 fast at 24 kW to 99 kW, 143 ultra fast at 100 kW or more), Victoria 311 (211 fast, 100 ultra fast). The same report put the national EV fleet above 410,000 in September 2025.

Networks named in the sources above include NRMA, Evie Networks and Chargefox, the state networks of Queensland and Western Australia, and the kerbside operators of the NSW program.

Site counts per network (for example for Chargefox and Evie Networks) appear only in secondary guides and were left out.

New Zealand

  • Connectors: the national guidance for public charging by Waka Kotahi (NZTA) recommends at least two tethered cables at a DC site, one CHAdeMO and one CCS2, because many cars are used imports from Japan with CHAdeMO and Type 1 inlets.
  • Early funding: the Low Emission Transport Fund run by the Energy Efficiency and Conservation Authority (EECA) co-funded public chargers in rounds. One announcement covered 16 projects with NZ$11 million of government money matched by NZ$13.5 million of private money, for more than 100 chargers and over 200 ports. An earlier goal of a charger about every 75 km of state highway was reached; the draft strategy Charging our Future proposed hubs every 150 km to 200 km.
  • Target: 10,000 public charge points by 2030, about one for every 40 EVs. The count was 1,378 on 31 December 2024 (government release, April 2025) and a bit over 1,800 in March 2026.
  • Loans: National Infrastructure Funding and Financing runs the EV Charging Infrastructure Loans programme. In March 2026 the government announced NZ$52.7 million in zero interest loans to ChargeNet and Meridian, who add about NZ$60 million of their own, for 2,574 charge points: 1,374 DC and 1,200 AC.

In this tool

  • A CCS2 session from either country is analysed like a European one: the shipped default limit profile (IEC 61851-1 and ISO 15118-2) applies, and it turns a PMax schedule into current at 230 V when the session does not name the voltage. See Limit profiles: the numbers behind every check.
  • A CHAdeMO session from a Japanese import is decoded by the CHAdeMO module from its CAN frames. See CHAdeMO: DC charging over CAN.
  • An OCPP-J log of the charger can be loaded beside the capture; it shows on the same timeline, which helps with the demand response and remote stop cases of South Australia. See OCPP 2.0.1 and ISO 15118: the backend behind the cable.

Sources