North America: J1772, CCS1, J3400 and the NEVI standards
How charging works and is regulated in the United States, Canada and Mexico: the J1772, CCS1 and J3400 connectors, the federal NEVI minimum standards in 23 CFR 680 (four 150 kW ports, 97 percent uptime, OCPP 2.0.1, ISO 15118, contactless payment), what happened to NEVI in 2025 and 2026, UL listing and weights and measures, the California rules, the AFDC counts, and the Canadian and Mexican picture.
Connectors: J1772, CCS1 and J3400
North America charges on the SAE family. AC uses the J1772 coupler, also called Type 1 (SAE J1772: the North American coupler and pilot). DC uses CCS1, which adds two DC contacts below the J1772 face, and increasingly SAE J3400, the connector Tesla opened as the North American Charging Standard (NACS) (SAE J3400: the NACS coupler). J3400 keeps the J1772 Control Pilot and the CCS protocols, so a capture from a J3400 session reads like a CCS1 capture. CHAdeMO remains on older cars.
- SAE published J3400 as a Technical Information Report on 18 December 2023 and released the Recommended Practice on 30 September 2024.
- Ford was the first large maker to announce a move to the connector, in May 2023. General Motors and Polestar followed in June 2023 and Mercedes-Benz in July 2023; Rivian, Volvo, Nissan and others followed.
- Toyota signed in October 2023 to adopt it from 2025, and Volkswagen, Audi, Porsche and Scout Motors announced it for 2025. Stellantis agreed in February 2024; select Stellantis EVs in North America get the J3400 inlet from model year 2026.
NEVI and 23 CFR 680
The National Electric Vehicle Infrastructure (NEVI) Formula Program of the Federal Highway Administration (FHWA) pays states to build fast charging along highway corridors. Its minimum standards, 23 CFR Part 680, were published on 28 February 2023 and took effect on 30 March 2023. They govern every charger funded under Title 23, not only NEVI.
| Area | What 23 CFR 680 requires | From |
|---|---|---|
| Ports and power | At least four DC ports per station, each with a CCS1 connector, able to deliver at least 150 kW to four cars at the same time | 30 March 2023 |
| Uptime | Each port reaches at least 97 percent average annual uptime over a five year operating period | 30 March 2023 |
| Charger to backend | OCPP 1.6J or higher at first; OCPP 2.0.1 | OCPP 2.0.1 within one year, so by 28 February 2024 |
| Charger to car | Conform to ISO 15118-3, hardware able to run ISO 15118-2 and ISO 15118-20; software conforming to ISO 15118-2 and able to do Plug and Charge | Software duty within one year, so by 28 February 2024 |
| Network to network | Communicate with other charging networks using OCPI 2.2.1 | Within one year |
| Payment | Several payment options without a membership fee, including contactless credit and debit cards, and either a toll free number or SMS to start and pay | 30 March 2023 |
| Data | Quarterly data reporting; FHWA collects it through the EV-ChART tool | With the rule |
J3400 in NEVI: according to summaries, FHWA allowed J3400 connectors on federally funded DC chargers from 2023 as long as each port also keeps a permanently attached CCS1 connector. In 2024 FHWA asked for comments on bringing J3400 into the federal requirements; CharIN answered on 5 April 2024.
Whether 23 CFR 680 has since been amended to name J3400, and the exact wording of the data and uptime clauses (680.108, 680.112, 680.114, 680.116), were not checked against the eCFR text for this page. The payment clause, 680.106(f), is quoted in Payment, roaming and Plug and Charge.
NEVI in 2025 and 2026
- From 6 February 2025 the Department of Transportation froze the NEVI funds that the states had not yet obligated. In June 2025 a federal court ordered them released, in Washington v. U.S. Department of Transportation.
- On 11 August 2025 FHWA issued an Interim Final Guidance that replaced all earlier NEVI guidance, gave states more freedom, for example on station spacing along corridors, and let them resubmit plans to use the FY2022 to FY2026 funds. The minimum standards of 23 CFR 680 stayed in force.
- The Eno Center for Transportation reported, from EV States Clearinghouse data of September 2025, 80 NEVI funded locations open with more than 370 fast chargers, and funds obligated for 990 stations and 3,932 fast chargers.
- Trade press reported that on 30 January 2026 the court ruled the 2025 freeze unlawful, which restored the access of the states to the funds.
NEVI is a moving target. Read the current FHWA guidance and the state plan before relying on any of these dates, and check the court ruling against the docket.
Safety, metering and California
- Safety: chargers are listed by a Nationally Recognized Testing Laboratory (NRTL) such as UL, Intertek (ETL) or TUV. AC equipment is listed to UL 2594 (Electric Vehicle Supply Equipment), DC equipment to UL 2202 (Electric Vehicle Charging System Equipment). The installation follows Article 625 of the National Electrical Code.
- Weights and measures: NIST Handbook 44, Section 3.40 (Electric Vehicle Fueling Systems) sets the accuracy and design rules for chargers that sell energy. NIST publishes the certificate of type approval format for EVSE under the national type evaluation program (NTEP).
- California, measurement: the Division of Measurement Standards (CDFA DMS) enforces Section 3.40. Commercial AC chargers installed from 1 January 2021 must comply, older ones by 1 January 2031; DC fast chargers installed from 1 January 2023 must comply, older ones by 1 January 2033. The California Type Evaluation Program (CTEP) lists approved chargers; NTEP certificates can be accepted if the device also meets California law.
- California, payment: the Air Resources Board (CARB) EVSE Standards regulation asks for an EMV chip and NFC card reader on each charger or a kiosk. DC fast chargers installed from 1 January 2022 must comply, and older DC fast chargers when they are replaced, at the latest by 1 July 2033. New Level 2 installations had to comply by 1 July 2023; older Level 2 chargers within five years of installation.
- California, reliability: the Energy Commission (CEC) adopted Charger Data and Reliability Standards in October 2025, effective 1 April 2026. Publicly or ratepayer funded DC ports installed from 1 January 2024 that do not serve fleets only must reach 97 percent uptime and report it; networked chargers installed from 28 September 2026 report through OCPP 2.0.1. Location, availability and price data go to third parties free of charge.
Later amendments of the CARB rule were not confirmed. Billing and measurement testing describes a Handbook 44 type evaluation and Safety and type approval of chargers and cars the UL tests.
How many chargers in the United States
The Alternative Fuels Data Center (AFDC) of the Department of Energy keeps the national station locator. InsideEVs reported that the public network passed 250,000 ports in June 2026: 250,406 ports at 80,543 locations. EVChargingStations.com counted, from AFDC data, 178,936 Level 2 ports on 22 June 2026 and 74,265 public DC fast ports, across all connector standards, on 1 July 2026.
How often those ports actually work is covered in Reliability of public charging: what field data says.
Canada and Mexico
- Canada, safety: CSA C22.2 No. 280 covers AC supply equipment up to 1000 V for cars with an on board charger; C22.2 No. 107.1 covers power conversion equipment; No. 281.1, No. 281.2 and No. 282 cover personnel protection and the couplers.
- Canada, metering: Measurement Canada oversees billing by energy under the Electricity and Gas Inspection Act. Since 2022 a temporary dispensation program lets eligible operators bill per kWh while type approval is being built; Measurement Canada gives the application deadlines as 31 December 2027 for AC and 31 December 2029 for DC, and the program ends on 1 January 2030. Only simple tariffs are supported so far.
- Canada, programs: the Zero Emission Vehicle Infrastructure Program (ZEVIP) of Natural Resources Canada funds chargers. In February 2026 the government announced 84.4 million dollars for 122 recipients and more than 8,000 chargers; Electric Autonomy reported that the public network then had more than 33,000 ports.
- Mexico: installations follow Article 625 of NOM-001-SEDE-2012. In February 2024 the Energy Regulatory Commission (CRE) sent a draft on electromobility to CONAMER. J1772 and CCS1 are the most used connectors, with GB/T and Tesla connectors also seen. The Electromobility Association (EMA) counted 56,726 charging positions at the end of 2025, of which more than 52,000 are private and just over 4,000 public.
Whether the DC type approval requirements of Measurement Canada are final, the status of the CRE draft, and a Mexican standard for connectors were not confirmed.
In this tool
- An EVSEID from US, CA, MX or PR, or a nominal supply of 120, 208, 240 or 277 V, makes the analyzer suggest the SAE J1772 and J3400 profile. It uses 240 V to turn a power schedule into current and allows 3 s (flagged for verification) for opening the contactor after C to B; see Limit profiles: the numbers behind every check.
- The CP checks read the J1772 pilot like the IEC one. J3400 and CCS1 sessions run through the same SL, HS, TL and SQ checks.
- NEVI asks for ISO 15118-2 and Plug and Charge: HS-02 shows whether the charger picks ISO 15118-2 or falls back to DIN SPEC 70121, and PK-01, PK-02 and the certificate chain tool read the charger certificates. The pnc-expired demo fails on an expired one.
- The OCPP tool reads OCPP 1.6 and 2.0.1 logs beside the capture, including the energy of each transaction.
The analyzer checks what happens on the wire. It does not test NEVI, Handbook 44 or California compliance. From OCPP logs it shows the uptime of each port as the logs show it, beside the 97 percent of NEVI; the outages the rule leaves out need the operator records, so that figure is no compliance verdict either.
Summary and further reading
| Aspect | United States | Canada | Mexico |
|---|---|---|---|
| AC connector | J1772 (Type 1); J3400 | J1772; J3400 | J1772 |
| DC connectors | CCS1, J3400; CHAdeMO on older cars | CCS1, J3400 | CCS1; GB/T and Tesla seen |
| Communication | PLC: DIN SPEC 70121, ISO 15118-2 (NEVI), ISO 15118-20 hardware readiness | PLC, as in the US | PLC, as in the US |
| Backend | OCPP 2.0.1 and OCPI 2.2.1 for NEVI; OCPP 2.0.1 reporting in California from 28 September 2026 | Not confirmed | Not confirmed |
| Key rules | 23 CFR 680 (28 February 2023); NEVI Interim Final Guidance (11 August 2025); CDFA DMS (2021 AC, 2023 DC); CEC reliability standards (1 April 2026) | Measurement Canada dispensations (from 2022); ZEVIP | NOM-001-SEDE-2012 Article 625 |
| Test and certification | NRTL listing to UL 2594 and UL 2202; NTEP and CTEP type evaluation | CSA C22.2 No. 280 and No. 107.1; Measurement Canada | Not confirmed |
Read on: SAE J1772: the North American coupler and pilot and SAE J3400: the NACS coupler for the connectors, OCPP: the charger's link to its backend for the backend, Highway and urban fast charging hubs for corridor charging, Payment, roaming and Plug and Charge for card payment, MCS: the Megawatt Charging System for trucks, and Charging around the world, Europe: AFIR, Type 2, CCS2 and ISO 15118 and Latin America: Type 2 and CCS2 in Brazil, Chile, Colombia, Argentina, Uruguay and Costa Rica for other markets. How EV charging is tested explains how chargers are tested.
Sources
- SAE J3400 technical information report and recommended practice, TIR 18 December 2023; recommended practice 30 September 2024
- Ford Authority: SAE standardizes NACS, January 2024
- Reuters factbox via StreetInsider: More automakers plug into Tesla's EV charging network, Ford May 2023, GM June 2023, Mercedes-Benz July 2023, Polestar June 2023
- Electrek: Toyota signs deal with Tesla for NACS and Supercharger access, 19 October 2023
- Ford Authority: Stellantis adopts NACS, February 2024; select vehicles from model year 2026
- Federal Register: National Electric Vehicle Infrastructure Standards and Requirements (23 CFR 680), final rule, 28 February 2023
- Foley: U.S. DOT finalizes EV charging infrastructure rules, effective 30 March 2023; OCPP 2.0.1, ISO 15118-2 Plug and Charge and OCPI 2.2.1 within one year
- Indiana DOT: Appendix B, NEVI requirements, four CCS1 ports at 150 kW, 97 percent uptime, ISO 15118, OCPP, payment
- FHWA: NEVI Formula Program Interim Final Guidance, 11 August 2025
- Electrification Coalition: NEVI Program updated guidance, funds frozen since 6 February 2025; plans due by 12 September 2025
- Congressional Research Service IN12556: Status of federal implementation of EV charging infrastructure
- Eno Center for Transportation: Washington v. U.S. Department of Transportation and NEVI progress updates, EV States Clearinghouse data, September 2025
- GreenCars: NEVI charging network reboots in 2026, court ruling of 30 January 2026
- ChargedEVs: FHWA requests comments on incorporating the NACS connector into federal requirements
- CharIN response to the FHWA RFI on SAE J3400, 5 April 2024
- IAEI Magazine: Understanding the components of EV charging systems, UL 2594, UL 2202, NEC Article 625
- CDFA DMS: NIST Handbook 44 Sections 3.30 and 3.40
- NIST: B-020 certificate of type approval, electric vehicle supply equipment
- CALeVIP: California EVCS Regulations Guide, DMS enforcement dates 2021, 2023, 2031, 2033; CTEP and NTEP
- CDFA DMS: California EVSE regulation reference document
- CARB: Electric Vehicle Supply Equipment Standards regulation, background and FAQs, EMV chip and NFC reader; Level 2 by 1 July 2023
- CARB: EVSE Standards, final regulation order, DC fast chargers from 1 January 2022, existing ones by 1 July 2033; Level 2 from 1 July 2023
- California Energy Commission: EV charger data and reliability standards, adopted October 2025, effective 1 April 2026
- E&E News: California approves first in the nation EV charger reliability rules
- InsideEVs: The U.S. now has over 250,000 EV charging ports, June 2026, AFDC data
- EVChargingStations.com: DC fast charging, July 2026, 74,265 public DC fast ports on 1 July 2026, AFDC data
- EVChargingStations.com: US now has over 170,000 public AC charging stalls, 178,936 Level 2 ports on 22 June 2026
- Standards Council of Canada: CSA Group notice of intent, electric vehicle supply equipment (C22.2 No. 280)
- Canadian Electrical Wholesaler: North American standards for EV charging stations, CSA C22.2 No. 280, 281.1, 281.2, 282
- Measurement Canada: Electric vehicle charging stations
- Measurement Canada: Temporary dispensation program for electric vehicle supply equipment, application deadlines 31 December 2027 (AC) and 31 December 2029 (DC); program ends 1 January 2030
- FLO: Energy billing guide, 28 April 2026; temporary dispensation deadlines, simple tariffs only
- Electric Autonomy: Ottawa announces $84.4 million investment for EV charging infrastructure, 11 February 2026
- Natural Resources Canada: Zero Emission Vehicle Infrastructure Program
- SecretarÃa de EconomÃa: NOM-001-SEDE-2012, electrical installations, Article 625, charging of electric vehicles
- Holland & Knight: CRE publishes draft on electromobility in CONAMER, 16 February 2024
- EVKX: SAE J1772 (Spanish), connectors used in Mexico
- vLex: Mexico reaches 56,726 chargers for electric cars in 2025, Electromobility Association barometer, end of 2025